Newcastle coastal revitalisation project update Wednesday, 07 October 2015

The main construction works for Shortland Esplanade Stage 1, Nobbys to Newcastle Ocean Baths, have now been completed with some supplementary works still ongoing including artwork, shade structures, furniture installations and planting of shade trees along the landscaped areas.

Works have started on Stage 2 of the Shortland Esplanade section of Bathers Way, Newcastle Ocean Baths to Zaara Street, and is scheduled to be completed in December 2015. In the coming months the area adjacent the baths intersection will be completed allowing improved pedestrian access around the rest of the work site. Piling will be undertaken throughout July to stabilise the embankment and support the work planned for the area.

Stage 2 Dixon Park to Bar Beach construction works are progressing well, with most pathways complete, light poles installed and shade shelters under construction. In the coming months ordinance fences, seating and other furniture elements will be installed, and planting works will be underway. This section is expected to be completed by spring 2015.

Update first published in Newcastle City Council's Winter News 2015 enewsletter. To access the original, click here.